Hazleton Library Renovation Schedule

Construction Schedule

Moving Dates and Temporary Locations

  • September/October 2018 – Schematic Design Phase
  • October/November 2018 – Penn State Leadership Approved Designs
  • December/January 2018/2019 – Penn State Leadership Approved Construction Documents
  • February/April 2019 – Permits Acquired
  • May/July 2020 – Construction
  • August 2020 – Library reopens

2020

July

  • Offsite storage items returned to newly renovated library building

July

  • Library temporary space closed and moved to newly renovated library building
  • Library computer lab closed and moved to newly renovated library building
  • Math Dimension closed and moved to newly renovated library building
  • Gina Monks and Nicole Young offices closed and moved to newly renovated library building

August

  • Library reopens